Hohhot Jiasheng New Energy Co., Ltd.(Hohhot WTE facility)
Processing Capacity (Daily):1750 t/d
Date of Investment:2017.11
Project Location:Hohhot, NeiMonggol Autonomous Region -
Zibo Green Energy Co., Ltd. (Linzi program)
Processing Capacity (Daily):4000 t/d
Date of Investment:In process
Project Location: Zibo Shandong -
Baishan Green New Energy Co., Ltd.(Baishan Program)
Processing Capacity (Daily):1000 t/d
Date of Investment:Preparing to build
Project Location:Baishan Jilin -
Linzhou Jiasheng New Energy Co., Ltd. (Linzhou Program)
Processing Capacity (Daily):1000 t/d
Date of Investment:Preparing to build
Project Location:Linzhou Henan -
Yunnan Jinde Green Energy Co., Ltd. (Puer program)
Processing Capacity (Daily):800 t/d
Date of Investment:Preparing to build
Project Location:Puer Yunnan -
Zhongwei Green New Energy Co., Ltd. (Zhongwei Program)
Processing Capacity (Daily):1000 t/d
Date of Investment:Preparing to build
Project Location:Zhongwei, Ningxia Hui Autonomous Region -
Yulin Green New Energy Co., Ltd. (Yulin program)
Processing Capacity (Daily):1000 t/d
Date of Investment:Preparing to build
Project Location: Yulin Shanxi -
Shijiazhuang Jiasheng New Energy Co., Ltd.(Shijiazhuang program)
Processing Capacity (Daily):2400 t/d
Date of Investment:In process
Project Location:Shijiazhuang, Hebei -
Tangshan Jiasheng New Energy Co., Ltd. (Tangshan WTE facility)
Processing Capacity (Daily):1000 t/d
Date of Investment:2019.6
Project Location:Tangshan Hebei